John Finlay Eng. & Tech. Group of Companies
Underground Paste Backfill Mining Solution

Singhali Underground Coal Mine
Short-Wall Interval Paste Backfill Recovery Plan

A green-mining solution to recover the trapped pillar coal of the 17E panel (G-III seam, Korba area) — lifting pillar recovery from 67.8% to 100% while controlling surface subsidence through engineered paste backfill, in line with NB/T 11433‑2023.

Engineered by John Finlay  •  India | Australia | China  •  50+ years in coal
8.45 Mt
Recoverable reserve (G-IIIT + G-IIIB)
67.8 → 100 %
Pillar recovery uplift
3.25 MPa
Design backfill strength
~81 %
Paste mass concentration
Watch the process

How paste backfill works — start to finish

A true side view: the coal seam is a thin horizontal layer sandwiched between sandstone roof and floor. The surface plant mixes waste gangue and ash into a paste, pumps it underground, and fills the voids in stages — so the standing pillars become one solid body and the ground above stays stable. Press Play, or click any stage.

Surface & structures ✓ Surface protected — no subsidence Surface batching plant cement fly ash gangue MIX PUMP Overburden ~46–130 m Sandstone roof fill pipeline G-III COAL SEAM — horizontal layer (~1.5–4 m thick) Seam floor (rock) CM
Stage 0 — Standing pillars
Room-and-pillar left coal pillars holding up the roof, with open roadways (hatched) between them along the horizontal seam.
Coal pillar Open / mined void Backfilled roadway B-strip paste A-strip paste Paste flow
The Opportunity

Recover what room-and-pillar left behind

The original re-mining concept recovered only part of the pillar coal through a slow two-pass cycle with 28-day waits. John Finlay's adjusted solution backfills the roadways first to lock the pillars into one ground-support monolith, then extracts every pillar strip — recovering effectively all the trapped coal.

⛏️

Maximise recovery

Pillar recovery rises from 67.8% to 100% — no 2 m sacrificial coal rib.

🏗️

Control subsidence

Cemented paste carries the overburden, controlling strata movement and surface settlement.

♻️

Use the waste

Gangue, fly ash and bottom ash become a non-segregating paste — no tailings dam.

Run in parallel

Mining and backfilling proceed simultaneously on different strips, lifting output.

Mining Sequence — plan view

48 pillars · 8 groups · A-B-C strips

Looking down on the panel: 48 pillars form 8 groups (I–VIII), each split into A, B and C strips. Extraction runs across all groups before changing strip: IB→VIIIB, then IA→VIIIA, then IC→VIIIC.

Phase 0 — Standing pillars
48 pillars with open roadways between them.
Paste Design & Strength

Engineered for a 3.25 MPa support body

Design strength is set by strip-pillar stability theory and fixed at 3.25 MPa using the conservative Bieniawski method.

Recommended paste mix (per m³)

Componentkg/m³Mass %Note
Coal gangue1,278.767.3%< 10 mm
Fly ash95.05.0%fine filler
Cement (OPC 425#)161.58.5%binder
Water361.019.0%
Admixture3.80.2%flow / set
Total1,900100%~81% solids

Strength development — gangue paste trials

UCS at 3 / 7 / 14 / 28 days. Higher solids and cement dosage drive strength past the 3.25 MPa design line.

Design basis: overburden load fully transferred onto the backfill; allowable strength by Bieniawski → [σ] ≈ 3.25 MPa. Cured paste does not de-water and gains strength over time.
Plant & Equipment

Surface paste batching station & delivery

Two independent systems run in parallel — coal haulage on the transport gateroad, paste pipeline on the return gateroad.

SystemEquipmentKey specificationQty
SilosCement silo220 m³ / 260 t1
SilosFly-ash silos330 m³ & 800 m³ (1,200 t)2
BatchingTwin-shaft mixerMAO 6000/4000, 2×55 kW1
PumpingIndustrial paste pumpHBMD150/14, 100–150 m³/h, 14 MPa2
PipelineVertical fill pipeØ219×18 mm, 16Mn200 m
PipelineMain fill pipeØ194×16 mm, quick-flange1,125 m
ControlPLC central controlSCADA + in-line pressure monitor1
AirEx screw compressor21 m³/min, 0.8 MPa, 132 kW2
Material flow: silo → weigh-batch → twin-shaft mixer → paste pump → Ø219 vertical pipe → Ø194 main pipe underground → flexible hose → sealed strip. Emergency-dump, pressure-test and pipe-switch valves rated to 20 MPa protect the line.
Solid-waste reuseNo tailings damIn-line pressure monitoringAutomated PLC batchingGroundwater-safe mix
Recovery & Economics

The case for the adjusted method

No sacrificial coal rib means pillar recovery reaches 100% against 67.8%. Some paste is re-mined when taking the A/B strips, but the value of the extra coal recovered exceeds that re-mining cost.

Incremental-recovery value calculator

Size the upside of going from 67.8% to 100% recovery. All inputs editable.

2.72 Mt
Extra coal recovered
$108.8 M
Incremental coal value
$70.7 M
Net upside after re-mining

Indicative only. Extra coal = resource × (100% − 67.8%). Replace with site coal price and verified paste cost for a bankable model.