FLL-1500WZ Centrifuge Information about the main parameters of the device
The user | |
The manufacturer | John Finlay |
Model | FLL-1500WZ |
Usage | Dewater |
Series No | FE02-24014 / JFE02-24015 |
Weight | 11754 kg |
Basket | Hefei John Finlay Mining Equipment Pty. Ltd. |
Equipment dimensions | 3310mm * 3165mm * 2192mm |
Drive motors | 75kW,380/660V,IP55,P6,3PH,50Hz |
vibration motor vibration motor | 415 V, the vibration motor is 8.4 kW,IP65,P4,3PH,50Hz |
Lubricating machine | 0.75kW,380/660V,IP55,P4,3PH,50Hz |
- Maintenance of the main components of the equipment
- Maintain schedules
Cycle | Contents | Operation | Notes |
weekly | Check the oil mark Routine inspection of oil quality Check the scale of the filter | If necessary, it will be raised If necessary, replace it Clean or replace the oil filter | |
Monthly | “Y” filter Vibrating motors Lubricating oil circuit and configuration Vibrating motors Transmission belts | cleanup Lubricate the motor – check the Condition of the stroke pointer Routine inspections, if necessary, repairs Check that the M36 bolts on the two vibrating motors are No fastening Re-tensioning – every 3.5-5.1 kg force required 20mm bending. | |
Every 3 months | Lubrication of Bearings on shafts Main bearings | Replace the automatic oiler on the spindle bearing Check the adjusting bearings | |
Half year | Bolts from the water tank to the sub-cube Shaft inlet part/polyurethane cover | Check the condition, replace it if it is old or deformed Check if necessary repairs Check the internal and external conditions | |
Basket replacement | basket holder The lining of the discharge section Infeed chute | Check the condition, replace it if it is old or deformed Check if necessary on repairs Check the internal and external conditions |
Notes:
- The first refuelling must be renewed after 500 hours of operation of the equipment and replaced every 2000 hours thereafter.
- Recommended oil Shell can withstand pressure S2-G100 (tank volume of about 40 L).The drive belt should be checked once after the first 24 hours of operation, and again after 80 hours of operation. Set the automatic oiler (” Simalub “SL-01) to be replaced every 3 months.
- Check the adjustment of the bearing/re-adjust the tightness of the expansion sleeve after one month of operation, and then once every 6 months.
Lubrication schedule
Specification | Lubricating oil sepcification | Lubricating oil quantity | Hours |
75KW driving motor,6 poles | L-XBCHA3 | 45g | 3000-4000 |
0.75KWLubricating machine,4poles | N.A- -Pre-oiled and sealed | ||
Vibrating motors | LGHP2 High-temperature grease | 60g | 500 |
fuel tank: Refueling for the first time Refueling afterwards | Shell pressure-resistant S2-G100 | 38-40L 38-40L | 500 2000 |
Spindle shaft oil seal | Automatic lubricator SL-01 | 3 months (adjustable) |
Precautions
It is strictly forbidden to weld, cut and do other hot operations on the water tank body to prevent the tiles and wear-resistant mud from falling off.
Before the operation of the equipment, the rotation direction of the vibration motor should be checked, and the rotation direction must be reversed. The basket should be cleaned before the operation of the equipment to prevent the basket or equipment from shaking